Client Confidential – EPC OF LNG PEAK SHAVING FACILITY – 2022
Location: Western United States
Awarded in June 2020, Matrix Service Company was contracted for the engineering, procurement, and construction of a new greenfield liquefied natural gas liquefaction facility.
The new facility is needed to meet system reliability for the supply of natural gas to customers in a major metropolitan area and its surrounding counties. The facility includes 15 million gallons of LNG storage capacity and 8.2 million standard cubic feet per day (MMSCFD) liquefaction capacity.
Construction began in the third quarter of the calendar year 2020 with an estimated in-service date in the fourth quarter of 2022.
15MM
gallons LNG storage capacity
8.2MMSCFD
liquefaction capacity
150MMSCFD
vaporization capacity
Scope of Work
- 15 MM gallons LNG storage capacity
- 8.2 MMSCFD liquefaction capacity
- 150 MMSCFD vaporization capacity
- Managed and installed ancillary equipment
- Managed and installed auxiliary equipment
- Installed utility systems
- Installation of stainless vacuum jacketed pipe
- Performed the engineering, procurement, and construction